COMPONENT-LEVEL ANALYSIS OF QUANTITY TAKE-OFF DEVIATIONS BETWEEN BIM AND CONVENTIONAL METHODS IN REINFORCED CONCRETE BRIDGE STRUCTURES

Authors

Indra Kusuma , Dedi Enda

DOI:

10.5281/zenodo.20655558

Published:

2026-06-12

Downloads

Abstract

Material quantity calculation is a critical stage in construction planning because the accuracy of quantity estimation directly affects project cost control and decision-making. In bridge construction, Quantity Take-Off (QTO) is commonly performed using conventional methods based on two-dimensional drawings, which may lead to quantity deviations due to geometric simplifications and limitations in representing complex structural details. This study aims to compare concrete and reinforcement quantities obtained using conventional methods and Building Information Modeling (BIM) through Autodesk Revit, as well as to identify the factors causing quantity deviations in bridge components. The research was conducted on the Tanjung Alai Village Bridge by developing a three-dimensional BIM model based on Detail Engineering Design (DED) drawings. Quantity comparisons were evaluated using percentage error and Root Mean Square Error (RMSE) analyses. The results showed average error values of 0.157% for concrete and 1.559% for reinforcement, with RMSE values of 0.015 m³ and 0.009 m³, respectively. The largest concrete deviation occurred in the Backwall due to its non-prismatic geometry, while the largest reinforcement deviation was found in the wing wall because BIM captured actual reinforcement length variations not fully represented in conventional calculations. These findings indicate that BIM provides reliable quantity estimation and a more detailed representation of structural geometry and reinforcement configurations in reinforced concrete bridge structures

Keywords:

Autodesk Revit Building Information Modeling (BIM) Quantity Deviation Analysis Quantity Take-Off (QTO) Reinforced Concrete Bridge

References

Adha, E. S. (2023). Penerapan Building Information Modeling (BIM) dalam perbandingan quantity take off material pada Jembatan Kecamatan Way Bungur Kabupaten Lampung Timur. Jurnal Rekayasa Sipil Dan Desain (JRSDD), 11(4), 715–724.

Asih, W. R., Husni, H. R., & Niken, C. (2022). Perbandingan Quantity Take Off ( QTO ) Material Berbasis Building Information Modeling ( BIM ) Terhadap Metode Konvensional pada Struktur Pelat. Jurnal Rekayasa Sipil Dan Desain (JRSDD), 10(4), 563–574.

Atmajaya, W., & Abma, V. (2025). Eksplorasi quantity take off ( QTO ) dan dampak terhadap biaya berbasis 5D BIM. Proceeding Civil Engineering Research Forum, 4(23), 155–166.

Farizah, D. (2024). Analisis Perhitungan Quantity Take Off Menggunakan Metode Bim (Revit) Beton Bertulang ( Studi Kasus : Proyek Jalan Tol Bangkinang – Pangkalan Pembangunan Jembatan Silam, Desa Silam, Kec. Kampar). Politeknik Negeri Bengkalis.

Nafiyah, R., & Martina, N. (2022). Analisis quantity takeoff pada pekerjaan struktur bawah jembatan. Construction and Material Journal. Proceeding Civil Engineering Research Forum, 4(2), 91–100.

Pratama, H., Aminullah, A., & Handayani, T. N. (2025). Implementation Of Building Information Modeling ( BIM ) For Bridge Abutment Cost Estimation Considering Qto Validity. 5(5), 4870–4885.

Purwanto, S., Satriawansyah, T., Tangerang, U. M., & Samawa, U. (2025). Integration of Building Information Modelling ( BIM ) in Civil Engineering Project : A Literature Review. 3(April), 319–326.

Reza, M., Fadlilah, N., Handayani, F. S., & Rifai, M. (2024). Analysis of Quantity Take Off Deviation Using BIM Method ( Case Study of Construction of a Satpol PP Building ). Sustainable Civil Building Management and Engineering Journal, c(3), 1–12. https://doi.org/10.47134/scbmej.v1i3.2828

Sadad, I., Jaya, F. H., & Januar, I. W. (2022). Implementasi BIM take off quantity material struktur abutment jembatan terhadap volume rencana. Jurnal Teknika Sains, 07(02), 91–97.

Setiawan, A. F., Fassa, F., & Kusuma, N. H. (2022). Analisis komparasi perhitungan volume pekerjaan struktur berdasarkan metode SPMI dan BIM. Jurnal RAB Construction Research, c(1), 20–35.

Stefanus Lutfiansyah, Y. (2025). Analisis Perbandingan Perhitungan Quantity Take-Off Metode Konvensional dengan Perhitungan Berbasis BIM Pada Pekerjaan Struktur Beton Jembatan. Jurnal Teknik Sipil, 21, 249–258. https://doi.org/10.28932/jts.v21i2.8560

Author Biographies

Indra Kusuma, Politeknik Negeri Bengkalis

Author Origin : Indonesia

Dedi Enda, Department of Civil Engineering, State Polytechnic of Bengkalis, Riau, Indonesia

Author Origin : Indonesia

Downloads

Download data is not yet available.

How to Cite

Kusuma, I., & Enda, D. (2026). COMPONENT-LEVEL ANALYSIS OF QUANTITY TAKE-OFF DEVIATIONS BETWEEN BIM AND CONVENTIONAL METHODS IN REINFORCED CONCRETE BRIDGE STRUCTURES. Multidiciplinary Output Research For Actual and International Issue (MORFAI), 6(4), 6072–6082. https://doi.org/10.5281/zenodo.20655558