QUANTITY TAKE-OFF COMPARISON OF CONVENTIONAL AND BIM-BASED CUBICOST METHODS: A CASE STUDY OF SMPN 2 MEGALUH

Authors

M. Bayu Fernando Syahfikri , Dedi Enda , Roma Dearni

DOI:

10.5281/zenodo.21704716

Published:

2026-07-30

Downloads

Abstract

Quantity Take-Off (QTO) is an essential process in construction projects as it directly influences cost estimation and project planning. Conventional quantity calculation methods often require more time and are prone to errors due to the manual interpretation of construction drawings. This study aims to compare the Quantity Take-Off results obtained using the conventional method and the Building Information Modeling (BIM) approach through Cubicost software in the construction project of SMPN 2 Megaluh. The BIM model was developed based on architectural, structural, and mechanical-electrical drawings using the Take-off for Architecture and Structure (TAS), Take-off for Reinforcement Bar (TRB), and Take-off for Mechanical, Electrical, and Plumbing (TME) modules. The quantities generated by Cubicost were then compared with those obtained through conventional calculations. The results indicate that most work categories produced relatively small deviations, demonstrating a good level of agreement between the two methods. The largest deviations in the TAS module were observed in ceiling works (15.93%) and earthworks (15.71%), while several work categories produced identical results. Quantity differences in the TRB and TME modules were generally influenced by modeling details, drawing interpretation, and calculation procedures. Overall, the BIM-based approach using Cubicost proved to be more efficient, integrated, and consistent in generating Quantity Take-Off data, making it a reliable alternative to conventional methods for construction quantity estimation.

Keywords:

Building Information Modeling (BIM) Quantity Take-Off Cubicost Construction Estimation Quantity Comparison

References

Azhar, S. (2011). Building Information Modeling (BIM): Trends, Benefits, Risks, and Challenges for the AEC Industry. Leadership and Management in Engineering, 11(3), 241–252.

Arifin, M. L. N., Hendrawangsa, P., & Sari, N. K. (2024). Bandingan Analisis Cost Budget Plan Menggunakan Metode Konvensional dan Metode Building Information Modeling (BIM) 5D dalam Pekerjaan Struktural. Akselerasi: Jurnal Ilmiah Teknik Sipil.

Eastman, C., Teicholz, P., Sacks, R., & Liston, K. (2018). BIM Handbook: A Guide to Building Information Modeling for Owners, Designers, Engineers, Contractors, and Facility Managers (3rd ed.). Hoboken, NJ: John Wiley & Sons.

Fernando, R., Friatmojo, E. K., Ricardo, K. C., & Khairunnisa. (2024). Perbandingan Quantity Take-off Baja Tulangan antara Metoda Konvensional terhadap Metoda BIM 5D Software Cubicost pada Struktur Gedung Fasilitas Perkeretaapian Manggarai. Orbith.

Fernando, R., Heston, Y. P., Wulandari, M., & Mahida, M. (2025). Analisis Perbandingan Efisiensi Perangkat Lunak BIM Autodesk Revit dan Software Cubicost dalam Quantity Take-off Penulangan. Orbith.

Hardin, B., & McCool, D. (2015). BIM and Construction Management: Proven Tools, Methods, and Workflows (2nd ed.). Indianapolis: Wiley Publishing.

Monteiro, A., & Martins, J. P. (2013). A Survey on Modeling Guidelines for Quantity Takeoff-Oriented BIM-Based Design. Automation in Construction, 35, 238–253.

Safri, & Hermania, T. O. (2024). Analysis of Waste Material Coefficient for Concrete Casting Work Using BIM Software Cubicost TAS. Applied Research on Civil Engineering and Environment (ARCEE).

Smith, P. (2014). BIM and the 5D Project Cost Manager. Procedia - Social and Behavioral Sciences, 119, 475–484.

Wibisono, M. Y., Satwiko, P., & Suyoto. (2025). Implementasi BIM dengan Software Glodon Cubicost dalam Estimasi Volume Pekerjaan Arsitektural. Vitruvian: Jurnal Arsitektur, Bangunan dan Lingkungan.

Author Biographies

M. Bayu Fernando Syahfikri, Department of Civil Engineering, Politeknik Negeri Bengkalis

Author Origin : Indonesia

Dedi Enda, Politeknik Negeri Bengkalis

Author Origin : Indonesia

Roma Dearni, Politeknik Negeri Bengkalis

Author Origin : Indonesia

Downloads

Download data is not yet available.

How to Cite

M. Bayu Fernando Syahfikri, Dedi Enda, & Roma Dearni. (2026). QUANTITY TAKE-OFF COMPARISON OF CONVENTIONAL AND BIM-BASED CUBICOST METHODS: A CASE STUDY OF SMPN 2 MEGALUH . Multidiciplinary Output Research For Actual and International Issue (MORFAI), 6(5), 7197–7204. https://doi.org/10.5281/zenodo.21704716

Similar Articles

1 2 3 4 5 6 7 8 9 10 > >> 

You may also start an advanced similarity search for this article.