ANALYSIS OF INDICATORS INFLUENCING DELAYS IN THE DEVELOPMENT OF ELECTRICAL POWER TRANSMISSION PROJECTS AT PLN UNIT INDUK PEMBANGUNAN JAWA BAGIAN TIMUR DAN BALI
DOI:
10.5281/zenodo.18454400Published:
2026-01-30Downloads
Abstract
Delays in electricity transmission projects within PLN UIP JBTB have become a dominant issue. The majority of projects during the 2020–2024 period experienced delays, as reflected by milestone deviations, cost overruns, and time overruns, which disrupted electricity supply reliability and adversely affected the company’s corporate image. This study aims to analyze the indicators that form latent variables influencing project delays using an explanatory qualitative approach with the PLS-SEM method. Primary data were collected through questionnaires from 140 respondents selected via purposive sampling, comprising project owners, technical experts, and consultants. The results indicate that the elimination of the indicator related to community resistance to the project suggests that project delays are not driven by overt social opposition, but rather by weak communication quality and insufficient community engagement. In the licensing factor, all indicators demonstrate that project delays result from the cumulative effects of slow processing, administrative unpreparedness, and weak inter-agency coordination. Regarding the financial factor, project delays are more strongly influenced by the project financial system’s ability to maintain cash flow continuity and cost control than by perceptions of the financial impact of delayed payments. The human resources factor confirms that project delays are associated with an imbalance between workload and workforce capacity, competence, productivity, and motivation. Meanwhile, the logistics and supply chain factor indicates that unprepared procurement and material distribution systems are a significant source of project delays, even when construction activities are technically well planned.
Keywords:
Electricity Transmission PLN UIP JBTB PLS-SEM Project DelayReferences
Andersen, E. S., Grude, K. V., & Haug, T. (2025). Goal Directed Project Management: Effective Techniques and Strategies. Taylor & Francis.
Arianie, G. P., & Puspitasari, N. B. (2017). Perencanaan Manajemen Proyek Dalam Meningkatkan Efisiensi Dan Efektifitas Sumber Daya Perusahaan (Studi Kasus: Qiscus Pte Ltd). J@ti Undip: Jurnal Teknik Industri, 12(3), 189–196. https://doi.org/10.14710/jati.12.3.189-196
Assaf, S. A., & Al-Hejji, S. (2006). Causes of delay in large construction projects. International Journal of Project Management, 24(4), 349–357.
Bakhtiyar, A., Soehardjono, A., & Hasyim, M. H. (2012). Analisis faktor-faktor yang mempengaruhi keterlambatan proyek konstruksi pembangunan gedung di kota lamongan. Rekayasa Sipil, 6(1), 55–66.
Cleland, D. I., & King, W. R. (1975). Competitive business intelligence systems. Business Horizons, 18(6), 19–28.
Ervianto, W. I. (2023). Manajemen Proyek Konstruksi. Penerbit Andi.
Hair, J., & Alamer, A. (2022). Partial Least Squares Structural Equation Modeling (PLS-SEM) in second language and education research: Guidelines using an applied example. Research Methods in Applied Linguistics, 1(3), 100027. https://doi.org/10.1016/j.rmal.2022.100027
Hartono, M., & Wiguna, I. P. A. (2023). Risk Analysis on The Construction Project of The 150 KV Bangkalan High Voltage Transmission Network. Journal of Economics and Business UBS, 12(4), 2223–2237. https://doi.org/10.52644/joeb.v12i4.369
Huh, I., & Gim, J. (2025). Exploration of Likert scale in terms of continuous variable with parametric statistical methods. BMC Medical Research Methodology, 25(1), 218. https://doi.org/10.1186/s12874-025-02668-1
Kamaruzzaman, S. N., Lou, E. C. W., Zainon, N., Mohamed Zaid, N. S., & Wong, P. F. (2016). Environmental assessment schemes for non-domestic building refurbishment in the Malaysian context. Ecological Indicators, 69, 548–558. https://doi.org/10.1016/j.ecolind.2016.04.031
Kaming, P. F., Koesmargono, A., & Aji, B. W. (2019). Delay model for Engineering Procurement Construction (EPC): A case of Liquefied Natural Gas (LNG) projects in Indonesia. MATEC Web of Conferences, 270, 05010. https://doi.org/10.1051/matecconf/201927005010
Liwoso, L. G., Setiono, S., & Sugiyarto, S. (2020). Identifikasi Dan Analisis Risiko Proyek Pada Masa Konstruksi Bangunan Bertingkat 4-40 Lantai Di Jabotabek Terhadap Ruang Lingkup, Jadwal, Dan Sumber Daya Proyek. Matriks Teknik Sipil, 8(2). https://doi.org/10.20961/mateksi.v8i2.45194
Madjid, U., & Saputri, N. E. (2021). Efektivitas Program Penghapusan 1000 Jamban Apung Di Kecamatan Martapura Barat Kabupaten Banjar Provinsi Kalimantan Selatan. Jurnal Academia Praja, 4(2), 496–508. https://doi.org/10.36859/jap.v4i2.664
Majid, M. Z. Abd., & McCaffer, R. (1998). Factors of Non-Excusable Delays That Influence Contractors’ Performance. Journal of Management in Engineering, 14(3), 42–49. https://doi.org/10.1061/(ASCE)0742-597X(1998)14:3(42)
Manlian, Manurung, E. H., Sitohang, O., Pio Ranap Naibaho, Faslih, A., Puro, S., Wardiningsih, S., & Suripto. (2023). Manajemen Proyek Konstruksi. Cendikia Mulia Mandiri.
Mulcahy, R. (2010). Rita Mulcahy’s Risk Management Tricks of the Trade for Project Managers: And PMI-RMP Exam Prep Guide: a Course in a Book. RMC Pub.
Orellano, M., & Gourc, D. (2025). What typology of risks and methods for risk management in innovation projects?: A systematic literature review. International Journal of Innovation Studies, 9(1), 1–15.
Rusdy, H. (2024). Strategi Peningkatan Laba Operasional PT Perusahaan Listrik Negara (PLN) Persero [Masters, Universitas Hasanuddin]. https://repository.unhas.ac.id/id/eprint/34682/
Sweis, G., Sweis, R., Abu Hammad, A., & Shboul, A. (2008). Delays in construction projects: The case of Jordan. International Journal of Project Management, 26(6), 665–674. https://doi.org/10.1016/j.ijproman.2007.09.009
Tjakra, J., & Sangari, F. (2011). Analisis resiko pada proyek konstruksi perumahan di Kota Manado. Jurnal Ilmiah Media Engineering, 1(1). https://ejournal.unsrat.ac.id/index.php/jime/article/view/4207
Zainuddin, Z., & Sujiat, S. (2021). Model Manajemen Resiko Proyek Insfrastruktur Perdesaan dengan Pendekatan Sistem Pembangunan Berkelanjutan. Teknika, 16(1), 24–35.
Zali, S., Mulyani, R., & Anif, B. (2025). Analisis Risiko Penyebab Keterlambatan Pekerjaan Konstruksi Gedung. Jurnal Teknik Sipil Institut Teknologi Padang, 12(1), 09–017.
License
Copyright (c) 2026 Gesmulyadi, I Putu Artama Wiguna

This work is licensed under a Creative Commons Attribution 4.0 International License.




