CONTRACTOR DECISION MAKING ON CONTINUING A SUSPENDED PROJECT USING AHP-TOPSIS (A CASE STUDI OF THE NINES PLAZA & RESIDENCE BSD PROJECT)

Authors

Jiwo Waskito , Endah Kurniyaningrum

DOI:

10.54443/morfai.v6i2.5011

Published:

2026-01-18

Downloads

Abstract

Suspended construction projects pose multidimensional challenges and necessitate accountable follow-up decision-making from the contractor’s perspective. This study develops a multi-criteria decision making (MCDM) framework to determine the most appropriate alternative for continuing a suspended high-rise building project, using the Nines Plaza and Residence BSD as a case study. The Analytic Hierarchy Process (AHP) is applied to derive priority weights for nine decision criteria, while the Technique for Order Preference by Similarity to Ideal Solution (TOPSIS) is used to rank four decision alternatives for project continuation. Decision robustness is examined through contextual scenario variations, respondent clustering based on expertise, and sensitivity analysis of criterion dominance. The results indicate that cost and financing are the most influential criteria, and continuing the project through a strategic partnership (joint venture) emerges as the best alternative. Robustness testing confirms that the decision outcome is stable and not driven by a single dominant criterion, demonstrating that the integrated AHP–TOPSIS approach is a suitable decision-support tool for contractors dealing with suspended construction projects.

Keywords:

Suspended Construction Project Multi-Criteria Decision Making AHP–TOPSIS Strategic Partnership In Construction Decision Model Robustness

References

Adepu, N., Kermanshachi, S., Pamidimukkala, A., & Loganathan, K. (2023). Analyzing the factors affecting construction project schedules amidst COVID-19 pandemic. Project Leadership and Society, 4, 100100. https://doi.org/10.1016/j.plas.2023.100100

Arfyan, A. R., Kurniyaningrum, E. ., Pontan, D., & Kusumawati, L. (2025). Analysis of Decision Making in Vendor Selection on the TKDN Value Limit Based on the Decree of the Minister of PUPR NO.602/KPTS/M/2023. Eduvest - Journal of Universal Studies, 5(5), 5317–5326. https://doi.org/10.59188/eduvest.v5i5.49995

Bartholomew, S. H. (2022). 16. Delays, Suspensions, and Terminations. In Construction Contracting. Virginia Tech Publishing. https://pressbooks.lib.vt.edu/constructioncontracting/chapter/delays-suspensions-and-terminations/

Begić, H., Galić, M., & Dolaček-Alduk, Z. (2022). Digitalization and Automation in Construction Project’S Life-Cycle: a Review. Journal of Information Technology in Construction, 27(October 2021), 441–460. https://doi.org/10.36680/j.itcon.2022.021

Behzadian, M., Khanmohammadi Otaghsara, S., Yazdani, M., & Ignatius, J. (2012). A state-of the-art survey of TOPSIS applications. Expert Systems with Applications, 39(17), 13051–13069. https://doi.org/10.1016/j.eswa.2012.05.056

Bunni, N. G. (2005). Restraints on the Execution of Works. https://fidic.org/sites/default/files/37 Restraints on the Execution of Works.pdf

Çevikbaş, M., & Işık, Z. (2021). An overarching review on delay analyses in construction projects. Buildings, 11(3), 109. https://doi.org/10.3390/buildings11030109

Chakraborty, S. (2022). TOPSIS and Modified TOPSIS: A comparative analysis. Decision Analytics Journal, 2, 100021. https://doi.org/10.1016/j.dajour.2021.100021

Chen, C. (2020). A Novel Multi-Criteria Decision-Making Model for Building Material Supplier Selection Based on Entropy-AHP Weighted TOPSIS. Entropy, 22(2), 259. https://doi.org/10.3390/e22020259

Construction Leadership Council. (2020). Advice on Temporary Suspension of Sites. https://www.constructionleadershipcouncil.co.uk/wp-content/uploads/2020/03/CLC_Advice-on-temporary-suspension-of-sites1.pdf

Darko, A., Chan, A. P. C., Ameyaw, E. E., Owusu, E. K., Pärn, E., & Edwards, D. J. (2019). Review of application of analytic hierarchy process (AHP) in construction. International Journal of Construction Management, 19(5), 436–452. https://doi.org/10.1080/15623599.2018.1452098

Hwang, C.-L., & Yoon, K. (1981). Multiple Attribute Decision Making: Methods and Applications: A State-of-the-Art Survey (1st ed.). Springer-Verlag. https://doi.org/10.1007/978-3-642-48318-9

International Project Management Association. (2016). Project Excellence Baseline for Achieving Excellence in Projects and Programes Version 1.0. International Project Management Association (IPMA). https://products.ipma.world/wp-content/uploads/2016/02/IPMA_PEB_1_0.pdf

Jäntschi, L. (2023). Eigenproblem Basics and Algorithms. Symmetry, 15(11), 2046. https://doi.org/10.3390/sym15112046

Khairurizqi, R. (2024). BSD City: Peluang Emas Investasi Properti di Masa Depan. Detik.Com. https://www.detik.com/properti/berita/d-7603203/bsd-city-peluang-emas-investasi-properti-di-masa-depan

Lafhaj, Z., Rebai, S., AlBalkhy, W., Hamdi, O., Mossman, A., & Alves Da Costa, A. (2024). Complexity in Construction Projects: A Literature Review. Buildings, 14(3), 680. https://doi.org/10.3390/buildings14030680

Mahatmantong, S., Moengin, P., Kurniyaningrum, E., & Pontan, D. (2025). Analisis Keputusan Pemilihan Vendor pada Proyek Infrastruktur Kawasan Ibu Kota Negara (IKN) dengan Menggunakan Metode Rank Order Centroid (ROC) dan Simple Multi Attribute Rating Technique (SMART). Syntax Literate: Jurnal Ilmiah Indonesia, Vol. 10(7), pp. 8758-8775

Ofori, G. (2023). Get Construction Project Performance Parameters Right to Attain Sustainable Development Goals. Sustainability (Switzerland), 15(18), 13360. https://doi.org/10.3390/su151813360

Park, C., Son, M., Kim, J., Kim, B., Ahn, Y., & Kwon, N. (2025). TOPSIS and AHP-Based Multi-Criteria Decision-Making Approach for Evaluating Redevelopment in Old Residential Projects. Sustainability (Switzerland), 17(15), 7072. https://doi.org/10.3390/su17157072

Petrović, G., Mihajlović, J., Marković, D., Hashemkhani Zolfani, S., & Madić, M. (2023). Comparison of Aggregation Operators in the Group Decision-Making Process: A Real Case Study of Location Selection Problem. Sustainability (Switzerland), 15(10), 8229. https://doi.org/10.3390/su15108229

Pindyck, R. S. (1993). Investments of uncertain cost. Journal of Financial Economics, 34(1), 53–76. https://doi.org/10.1016/0304-405X(93)90040-I

Polit, D. F., & Beck, C. T. (2006). The Content Validity Index: Are You Sure You Know What’s Being Reported? Critique and Recommendations. Research in Nursing & Health, 29(5), 489–497. https://doi.org/10.1002/nur.20147

Rauzana, A., & Dharma, W. (2022). Causes of delays in construction projects in the Province of Aceh, Indonesia. Plos One, 17(1), 1–12. https://doi.org/10.1371/journal.pone.0263337

Saaty, T. L., & Vargas, L. G. (2012). Models, Methods, Concepts & Applications of the Analytic Hierarchy Process (2nd ed.). In International Series in Operations Research & Management Science. Springer. https://doi.org/10.1007/978-1-4614-3597-6

Sund, S., Sendstad, L. H., & Thijssen, J. J. J. (2022). Kalman filter approach to real options with active learning. Computational Management Science, 19(3), 457–490. https://doi.org/10.1007/s10287-022-00423-1

Author Biographies

Jiwo Waskito, Universitas Trisakti

Author Origin : Indonesia

Endah Kurniyaningrum, Universitas Trisakti

Author Origin : Indonesia

Downloads

Download data is not yet available.

How to Cite

Jiwo Waskito, & Endah Kurniyaningrum. (2026). CONTRACTOR DECISION MAKING ON CONTINUING A SUSPENDED PROJECT USING AHP-TOPSIS (A CASE STUDI OF THE NINES PLAZA & RESIDENCE BSD PROJECT). Multidiciplinary Output Research For Actual and International Issue (MORFAI), 6(2), 2443–2455. https://doi.org/10.54443/morfai.v6i2.5011

Similar Articles

1 2 3 4 5 6 7 8 9 10 > >> 

You may also start an advanced similarity search for this article.